Question description

Earned ValueI have most of the values calculated. ¬†Looking for help with the rest…
Task
Budget Cost (PV)
Budget Duration
Status as of Week 13
AC
EV
CV
CPI
A
$5,000.00
2
100%
$5,000.00
$5,000.00
$0.00
1
B
$8,500.00
3
100%
$9,000.00
$8,500.00
-$500.00
0.944444444
C
$15,000.00
4
75%
$14,000.00
$11,250.00
-$2,750.00
0.803571429
D
$10,000.00
4
50%
$9,000.00
$5,000.00
-$4,000.00
0.555555556
E
$12,000.00
4
0%
$0.00
$0.00
$0.00
0
F
$15,000.00
5
0%
$0.00
$0.00
$0.00
0
TOTALS
$65,500.00
$37,000.00
$29,750.00
-$7,250.00
0.804054054
CV = EV-AC
-7250
Project is over
budget
CPI = EV/AC
0.804054054